AEC - Express Pipeline SCADA Project

Alberta Energy Company Ltd. (AEC) is the owner and operator of the new Express Pipeline, which delivers crude oil from Hardisty, Alberta, to Casper, Wyoming. The 785 mile long pipeline is 24 inches in diameter and has a capacity of 172,000 barrels per day.

AEC selected Emerson Process Management as their automation consultant to help them in meeting their "fast track" schedule for designing and implementing a pipeline SCADA system. The SCADA system was to be completed in 12 months - half the time of a typical pipeline SCADA project of this magnitude.

The project scope included hardware/software specification and procurement, detailed engineering, configuration, integration, testing, installation, commissioning, and training. Emerson Process Management also developed detailed specifications for Power Optimization Software and Oil Movements Scheduling / Accounting Software.

The ability to perform under stressful situations, which was anticipated as a result of the fast track nature of the project, was a primary concern to our client and us. A project room, with all SCADA and HMI equipment, was established at the SCADA vendor's facility to ensure timely, effective, and constant interaction between the owner, consultant, and vendor. We were able to resolve problems quickly because project team members could easily congregate and develop solutions. Establishing this common work environment was one of the most significant decisions of the project and it enabled the complex pipeline control and custody measurement system to start up with all functionality in place.

This project illustrated that fast track SCADA projects can be implemented on time and on budget with high quality results. Strong project management and a focused and committed project team that communicated effectively was critical to Emerson Process Management's success on this SCADA project.

Control and Information  Advanced Control
.
   Search Process Solutions search industry solutions
• Emerson chosen to digitally automate North West Upgrading's $2.6 billion dollar oil sands project 

• Emerson awarded contract for digital automation of first phase of $9.4 billion Horizon Oil Sands Project in Canada

• Emerson completes digital automation engineering and design for $12 billion Liquefied Natural Gas project in Qatar

• Suncor Energy selects Emerson for automation solutions for North American refineries and oil sands facilities

• BP awards Emerson a major automation contract for upgrades at refiner's three largest U.S. facilities

•  Emerson SIS engineers are first to be certified by TÜV to IEC 61511
 
• Weyburn PLC and HMI Upgrade Project

• NOVA Chemicals - J2000 Project

• BC Gas - Natural Gas Pipeline PLC Project

• AEC - Express Pipeline SCADA Project
 
 

Global Petroleum Show
June 10 – 11 Calgary, Alberta

ISA Canada
April 9-10 Edmonton, Alberta

 

Explore Career Opportunities with
Emerson's Hydrocarbon & Energy Center

Send Comments to:
InfoCentral@EmersonProcess.com

Š Emerson, 1998-2008
Legal and Privacy Statements